Ten years and $9 million

Tuesday, Jun 24, 2025 - Posted by Rich Miller

* More than eight years after the old station was destroyed, a groundbreaking ceremony was held for a new station, which won’t be completed for another two years and is projected to cost almost $9 million

The 115th Street Morgan Park Metra stop along the Rock Island Line is set for a major renovation, with members of the Metra Board of Directors and local officials recently gathering for a ground-breaking ceremony.

On June 16, Metra began the $8.69-million project to improve the 115th Street Morgan Park Station on the Rock Island Line.

The renovation, expected to be completed in 2027, will replace the existing platform shelters, create a new plaza and sidewalks, and address stormwater management needs.

Since 2017, the 115th Street Morgan Park stop has not had a depot. The original station, located at 1982 W. 115th St., sustained extensive damage from a fire in May 2017 and was later demolished.

* This is what commuters are getting for almost $9 million…

Not trying to pick on Metra here, just pointing out how long it takes to build anything - and how expensive it is.

* Of course, that little station pales in comparison to the $80 million Damen Green Line Station and is barely a speck of dust next to the CTA’s $5.75 billion Red Line extension - which works out to a mind-boggling billion dollars per mile.

* The High Speed Rail Association looked at this a few years ago

One factor is the inappropriate use of consultants in the U.S. “Oftentimes, what we’ve found is that consultants are brought on to answer the questions of, What do we need to be doing?” [Eric Goldwyn, who leads the Transit Costs Project], said in a recent interview with the publication Governing. “Rather than an agency telling the consultant what they need to be doing, the consultant starts to do stuff, and the agency is like, ‘Well, that’s not really what we want. We need you to go study this other thing.’ They’re billing you by the hour and those costs accumulate.”

Labor costs are a second driver of the high costs. The issue isn’t wages per se, since most European countries pay equivalent or higher wages for construction work. It’s more about the overall number of workers employed on projects, along with the deference to car culture in the U.S.—which not only slows down projects but leads to workers being paid for overtime and overnight shifts. “If you don’t let a lane or two of traffic be shut down so they can dig a big hole,” Goldwyn said, “that just means they’re going to dig it much more slowly, and they’re going to have to dig it at weird hours of the day, so it’s going to be much more expensive. If you just said, ‘Yeah it’s going to be annoying, but let’s just do it and get it over with,’ that would be, I would argue, a better way to go.”

The relative lack of standardization in U.S. projects is a third key factor. Countries with lower construction costs emphasize standardization and “really trying to economize as much as possible,” according to Goldwyn. “In the States, we have this tendency to customize and make everything bespoke,” he said in the Alliance webcast. “The issue is that if you’re designing everything as one-off, you don’t save any money in your design,” and you can’t apply the lessons learned—or the potential cost savings—moving forward.

A fourth factor is that there are so many stakeholders with their own agendas in the U.S. “One of the things that’s interesting in this research is how often government agencies or utility companies gum up these projects because they want something” in exchange for doing their job, Goldwyn said. “There’s all these opportunities for extraction, and there needs to be someone at a high enough power, like a mayor, who is saying, ‘Cut the crap. We need to get this done. . . . You can’t keep trying to extract more and more bribes from these megaprojects.’”

Discuss.

* Related…

       

19 Comments »
  1. - Just Me 2 - Tuesday, Jun 24, 25 @ 12:48 pm:

    I don’t have the details on this project, but typically Metra doesn’t build or manage the neighborhood stations. Metra is responsible for the platform and it is the municipality that is responsible for the station around it.

    There are exceptions of course.


  2. - Just Me 2 - Tuesday, Jun 24, 25 @ 12:50 pm:

    Oh, and it is also expensive to build around a functioning rail line as the trains come by so frequently and for safety reasons work has to of course stop, but also equipment staging is also a real pain in the you-know-what.


  3. - Jurist - Tuesday, Jun 24, 25 @ 12:56 pm:

    Also, it’s a flag stop with low ridership compared to the other Rock Island-Beverly branch stops. The HSRA article is a great reference, thanks for sharing.


  4. - DuPage Saint - Tuesday, Jun 24, 25 @ 1:00 pm:

    The article mentioned standardization and I think that is a key. Have several different designs and use them over and over. You would save costs and time. Fast food joints do not have to reinvent the wheel every time hey build


  5. - Chicagonk - Tuesday, Jun 24, 25 @ 1:05 pm:

    And they could have just put the money into the Rock Island and Metra Electric lines.


  6. - Cool Papa Bell - Tuesday, Jun 24, 25 @ 1:10 pm:

    =just pointing out how long it takes to build anything=

    Transit adjacent. I think of this every time I pass the torn down rest stops just north of Springfield. I think its going to be 2+ years (maybe more) from the time they were closed, torn down and rebuilt.

    We are talking about what 2000 square feet with 15 bathroom stalls and a lobby? That’s a job that takes more than 2 years?

    I guess the “cut the red tape” line is as over used as the “waste, fraud and abuse” line is. But I sure wish we as a state could find a way to move these projects along.


  7. - NorthSideNoMore - Tuesday, Jun 24, 25 @ 1:12 pm:

    Wondering if ridership matters may have contributed to the delay/need to replace the old one.


  8. - Quad Cities - Tuesday, Jun 24, 25 @ 1:14 pm:

    The blue state challenge - completing projects!
    In 2010, the new Chicago-to-Moline train was announced with fanfare. Moline and surrounding cities with federal help built a new train station and hotel to prepare for what was supposed to come in 2015. The year is 2025 and the project hasn’t started.


  9. - Old IL Dude - Tuesday, Jun 24, 25 @ 1:18 pm:

    Was hoping that the nearly $6B for the Red Line extension could be reimagined as $1B for AI-assisted bus rapid transit on a similar route. The remaining cash could be used for the so-called transit cliff.


  10. - Rich Miller - Tuesday, Jun 24, 25 @ 1:21 pm:

    ===The remaining cash could be used for the so-called transit cliff.===

    Horrible idea to use one-time money for ongoing expenses.


  11. - Google Is Your Friend - Tuesday, Jun 24, 25 @ 1:36 pm:

    Not saying this couldn’t be done less expensively or better, but it seems like an expensive key here is “and address stormwater management needs.”


  12. - Old IL Dude - Tuesday, Jun 24, 25 @ 1:40 pm:

    Rich, you think the $6B for the Red Line extension is a wise idea? It’s over $1M per foot. The Amtrak higher speed rail project from Chicago to STL was less than $2B and that was 284 miles. Ay yi yi …


  13. - ArchPundit - Tuesday, Jun 24, 25 @ 1:41 pm:

    —The article mentioned standardization and I think that is a key. Have several different designs and use them over and over.

    I don’t think they have to be replicas, but reusing design elements alone could help a lot instead of starting from scratch.

    Part of the consultant problem is we don’t keep some of that expertise on staff. While that’s a cost, employees tend to understand the goal better. In some cases, yes the accounting sucks, but we could also share employees between agencies.


  14. - OneMan - Tuesday, Jun 24, 25 @ 1:42 pm:

    One way to do it faster. A 3D-printed train
    station in Japan. It’s too small, and the like, but overall it’s an interesting idea.

    https://www.youtube.com/watch?v=182f3gk2eB0


  15. - James the Intolerant - Tuesday, Jun 24, 25 @ 2:45 pm:

    It is a $9M warming station.
    One would think since Metra payes $30M annually for a Project Management Organization they could do better.
    As stated earlier, very low ridership station.


  16. - Simon R. - Tuesday, Jun 24, 25 @ 2:46 pm:

    == just pointing out how long it takes to build anything - and how expensive it is. ==

    Amen. This is the subject of Ezra Klein’s new book “Abundance.” It’s a must read for Democratic policy makers.

    Here’s another example of this problem from the “City That Works” Substack on the Red Line extension:

    “In 1985, the CTA’s Final EIS (Environmental Impact Study) for the Orange Line ran 378 pages. The 2022 Final EIS for the Red Line Extension is 50 times longer, at 17,899 pages. That’s for a project that’s half as long.”

    An EIS is all well and good, but c’mon. Good intentions can become a ridiculous burden. You can see evidence of this if you read the full Metra station story linked above. A local NGO didn’t think the $9 million was good enough….wanted a grander station more aligned with local architecture. Again, well intended, but expensive and time consuming.

    We have to do better.


  17. - walker - Tuesday, Jun 24, 25 @ 3:23 pm:

    “”Ezra Klein’s new book “Abundance.” It’s a must read for Democratic policy makers”"
    . Yes SimonR ++

    He calls out Chicago housing advocates and supporters especially, as unintentionally causing our own shortfalls on affordable housing.


  18. - Amalia - Tuesday, Jun 24, 25 @ 4:30 pm:

    so maybe the stormwater management issues include addressing that on the plaza that is also being constructed. still seems like lots of money for this station. but, if we’re doing comparisons, how much money did the Legislature provide for some school project in the district of the Speaker? and, yes, the Red Line extenstion is too expensive.


  19. - Blake - Tuesday, Jun 24, 25 @ 4:35 pm:

    This is the kind of thing both in time & cost that drives me towards Abundance


TrackBack URI

Anonymous commenters, uncivil comments, rumor-mongering, disinformation and profanity of any kind will be deleted.

(required)

(not required)



* Isabel’s afternoon roundup
* Musical interlude: Mick Ralphs
* Ten years and $9 million
* Question of the day
* Pritzker to announce reelection bid Thursday, sources say
* It’s almost a law
* Caption contest!
* Why Are Tax-Exempt Hospitals Getting Rich?
* Open thread
* Isabel’s morning briefing
* SUBSCRIBERS ONLY - Supplement to today’s edition
* SUBSCRIBERS ONLY - Today's edition of Capitol Fax (use all CAPS in password)
* Selected press releases (Live updates)
* Live coverage
* SUBSCRIBERS ONLY - This just in
* Yesterday's stories

Support CapitolFax.com
Visit our advertisers...

...............

...............

...............

...............


Loading


Main Menu
Home
Illinois
YouTube
Pundit rankings
Obama
Subscriber Content
Durbin
Burris
Blagojevich Trial
Advertising
Updated Posts
Polls

Archives
June 2025
May 2025
April 2025
March 2025
February 2025
January 2025
December 2024
November 2024
October 2024
September 2024
August 2024
July 2024
June 2024
May 2024
April 2024
March 2024
February 2024
January 2024
December 2023
November 2023
October 2023
September 2023
August 2023
July 2023
June 2023
May 2023
April 2023
March 2023
February 2023
January 2023
December 2022
November 2022
October 2022
September 2022
August 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
December 2020
November 2020
October 2020
September 2020
August 2020
July 2020
June 2020
May 2020
April 2020
March 2020
February 2020
January 2020
December 2019
November 2019
October 2019
September 2019
August 2019
July 2019
June 2019
May 2019
April 2019
March 2019
February 2019
January 2019
December 2018
November 2018
October 2018
September 2018
August 2018
July 2018
June 2018
May 2018
April 2018
March 2018
February 2018
January 2018
December 2017
November 2017
October 2017
September 2017
August 2017
July 2017
June 2017
May 2017
April 2017
March 2017
February 2017
January 2017
December 2016
November 2016
October 2016
September 2016
August 2016
July 2016
June 2016
May 2016
April 2016
March 2016
February 2016
January 2016
December 2015
November 2015
October 2015
September 2015
August 2015
July 2015
June 2015
May 2015
April 2015
March 2015
February 2015
January 2015
December 2014
November 2014
October 2014
September 2014
August 2014
July 2014
June 2014
May 2014
April 2014
March 2014
February 2014
January 2014
December 2013
November 2013
October 2013
September 2013
August 2013
July 2013
June 2013
May 2013
April 2013
March 2013
February 2013
January 2013
December 2012
November 2012
October 2012
September 2012
August 2012
July 2012
June 2012
May 2012
April 2012
March 2012
February 2012
January 2012
December 2011
November 2011
October 2011
September 2011
August 2011
July 2011
June 2011
May 2011
April 2011
March 2011
February 2011
January 2011
December 2010
November 2010
October 2010
September 2010
August 2010
July 2010
June 2010
May 2010
April 2010
March 2010
February 2010
January 2010
December 2009
November 2009
October 2009
September 2009
August 2009
July 2009
June 2009
May 2009
April 2009
March 2009
February 2009
January 2009
December 2008
November 2008
October 2008
September 2008
August 2008
July 2008
June 2008
May 2008
April 2008
March 2008
February 2008
January 2008
December 2007
November 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
October 2006
September 2006
August 2006
July 2006
June 2006
May 2006
April 2006
March 2006
February 2006
January 2006
December 2005
April 2005
March 2005
February 2005
January 2005
December 2004
November 2004
October 2004

Blog*Spot Archives
November 2005
October 2005
September 2005
August 2005
July 2005
June 2005
May 2005

Syndication

RSS Feed 2.0
Comments RSS 2.0




Hosted by MCS SUBSCRIBE to Capitol Fax Advertise Here Mobile Version Contact Rich Miller