* Bloomberg….
The largest US grid is proposing a “fast energization” plan to speed up connection for data centers and power plants in response to criticism from regulators that PJM Interconnection LLC is struggling to keep pace with surging demand while costs rise for consumers.
PJM has developed a process that would cut the time needed to study proposed data center connections to its 13-state grid to 12 months from 24. The plan would review proposed power plants and transmission upgrades in parallel, according to a 1,067-page filing with the Federal Energy Regulatory Commission late Monday.
For the first time, PJM will consolidate studies of new power plants, transmission upgrades and the addition of new big users rather than evaluating them through separate processes.
*Press release…
Why PJM Is Proposing Fast Energization
Neither generation nor transmission is coming online quickly enough to keep pace with new demand growth driven mainly by Large Loads like data centers. The factor that PJM Planning can influence is how quickly these new resources are studied for reliability.
Transmission service for Large Loads is addressed in different processes, making it difficult for states to understand all the costs being driven by Large Load development.
Large Loads differ fundamentally from traditional load growth in size, pace and concentration, and they are the only major source of load growth. FERC found that new transmission services should be available to reflect the operational reality that some Large Loads are willing and able to limit their use of the transmission system, including an interim service while Network Upgrades are constructed.
* Reuters…
PJM Interconnection, which covers 13 US Mid-Atlantic and Midwest states, has struggled to keep up with the rising electricity needs brought by Big Tech’s rapid data center expansion that began roughly three years ago.
That supply and demand crunch has triggered a sharp rise in power bills in a region covering 67 million Americans and a roughly 6.8 gigawatt electricity supply shortfall that threatens the reliability of the grid if new power supplies are not secured on time. […]
Data center advocates have pushed back against earlier discussions of the combined study process, with the trade group Data Center Coalition telling the PJM board in October that the combined process might complicate the grid interconnection process and ultimately lead to longer delays in connecting power plants and data centers.
PJM is asking that FERC begin a 60-day comment period on its proposed plan and issue a ruling within 120 days.
* Related…
* Utility Dive | PJM urged to delay base capacity auction until data centers cut from forecast: So far, including existing and forecast data center demand in PJM’s capacity market has increased capacity costs by $29.4 billion for all customers, according to Monitoring Analytics’ Nov. 12 report that called for the auction to be postponed. PJM has responded to pressure from states, federal regulators and consumers by proposing a two-part plan to meet data center demand by facilitating bilateral contracts outside its normal capacity auctions, and also holding a backstop procurement for large loads that do not have bilateral contracts. It is also pursuing reforms to its rules for interconnecting large loads and generating supplies. The status of these efforts is pending.
* STLPR | Midwest grid operator justifies data center policy amid concerns about rising utility costs: The grid operator said in its report Monday that federal regulators are concerned that its policy lacks guardrails to prevent grid upgrade costs shifting to consumers. The commission suggested additional transparency measures and stronger cost-shifting safeguards. In response, MISO proposed a transparency dashboard for large load projects and two new agreements that make transmission customers, such as utility providers, responsible for all grid upgrade costs identified in the grid operator’s project review process. MISO said in its report that it has successfully managed large users so far, touting reliability and efficient integration of new users onto the grid.
* CNI | Lessons from 3 communities: Report details resident concerns about data centers: Data centers have dominated public discourse over the last year, but much analysis of their effects has relied on limited information, because of a lack of public sources, according to a new report from the University of Illinois. The state keeps no master list, no single agency oversees them, zoning is handled by local municipalities, environmental and utility connection oversight is split, and few companies report water and energy use on a voluntary basis. That means that, when residents have concerns, few resources are available to answer their questions.